BOARD MEETING DATE: May 6, 2005
AGENDA NO. 13

PROPOSAL:

Amend Contracts to Provide Short- and Long-Term Systems Development and Support Services

SYNOPSIS:

The AQMD currently has contracts with several companies for short- and long-term systems development services. These contracts are periodically amended to add budgeted funds as additional needs are defined. This action is to amend the contracts approved by the Board to add additional funding for needed development work. Funds for this purchase are included in the FY 2004-05 Budget.

COMMITTEE:

Administrative, April 8, 2005, Recommended for Approval

RECOMMENDED ACTION:

Authorize the Executive Officer to execute amendments to the contracts for systems development services in the total amount of $95,000: $45,000 to Applied Knowledge and $50,000 to CMC Americas.

Barry R. Wallerstein, D.Env.
Executive Officer


Background

At the November 1, 2002 meeting, the Board authorized staff to initiate level-of-effort contracts with several vendors for system development and support services. At the time these contracts were executed, it was expected that they would be modified in the future to add funding from approved budgets as system development requirements were identified and sufficiently defined so that task orders could be prepared.

The contracts are Basic Ordering Agreements: Individual task orders are issued on both a competitive and sole-source basis (depending on the size and complexity of the system), after review of prior successful experience of the company and associated administrative costs of the bid process relative to the costs associated with the work effort. System development efforts are currently needed (see Attachment 1) to enhance system functionality and to provide AQMD staff with additional automation for improving productivity. The estimated cost to complete the work on these additional tasks exceeds the amount of funding in the existing contracts.

The current contracts are for one year with the option to renew for two one-year periods. Renewal of these contracts is contingent upon performance, competitiveness, percent of tasks bid and overall customer satisfaction.

This item is listed on the "Status Report on Major Projects for Information Management."

Proposal

Staff proposes the contracts be amended to add additional funding ($95,000) in the amounts of $45,000 to Applied Knowledge and $50,000 to CMC Americas for the specific task orders listed in Attachment 1.

Resource Impacts

Sufficient funding is included in the FY 2004–05 Budget.

Attachment

Attachment 1 – Task Orders Summary

 

ATTACHMENT 1
Task Orders Summary

Section A – Funding Totals by Contract
 

Contractor

Previous
Funding

This
Addition

Total
Funding

Applied Knowledge, Inc.

$406,000

$45,000

$451,000

CMC Americas

$402,000

$50,000

$452,000

R Systems, Inc.

$742,000

0

$742,000

TOTAL

$1,550,000

$95,000

$1,645,000

Section B – Task Orders Scheduled for Award
 

Task

Description

Estimate

Facility Permit System Enhancements

Enhance the Facility Permit System to support change of ownership processing and other user defined administrative and printing functions

$40,000

Title V Tracking Integration

Modify the Permitting System(s) to provide Title V tracking and administrative functions

$20,000

Telemetry System Enhancements

Enhance the Telemetry System to provide additional tracking and editing capabilities

$10,000

R222 System Web-Based Filing

Develop on-line system to process equipment exempt from permit requirements (R222 Filings)

$25,000

 

TOTAL

$95,000

/ / /