REPORT:
Summary of Changes to FY 2004-05 Approved Budget
SYNOPSIS:
This is the annual report of budget changes for FY 2004-05.
COMMITTEE:
Not Applicable
RECOMMENDED ACTION:
Receive and file.
Barry R. Wallerstein, D.Env.
Executive Officer
Background After the close of each fiscal year, staff has prepared and presented to the Board a report of midyear revisions to the budget. The attached Board-approved budget changes reflect actions taken by the Board to increase the budget. In addition, there were organizational unit-requested budget changes that did not increase the budget but reallocated already-budgeted funds within a Major Object to meet operational needs. Organizational unit-requested budget changes included such things as a transfer from District General to Information Management to implement optional expedited permit processing [Rule 301(y)]; transfers from Engineering & Compliance to Information Management for a RECLAIM RTC QCER Settlement Report, PPS maintenance and enhancements, Title V tracking software maintenance, and NSR and facility permit maintenance and enhancements; and a transfer from Science & Technology Advancement to Information Management to develop on-line registration software for the 2005 Lawn Mower Exchange Program. All expenditures relating to budget increases and/or transfers follow Board-established policy regarding purchasing and contracting. BOARD-APPROVED BUDGET CHANGES:
Date of
Board Action |
Budget
Increases |
|
Description |
| |
|
|
|
| June 2004 |
$ 900,000 |
|
Funds from the Department of Defense to conduct a
feasibility demonstration to measure low-level pollutant concentrations.
|
| July 2004 |
450,000 |
|
Funds from the Clean Fuels Fund for technical assistance,
expert consultations, public outreach and technical conference
sponsorship, Science & Technology Advancement website upgrades to support
clean fuels program activities, and advanced technology vehicle leases.
|
| July 2004 |
668,000 |
|
Funds from the Clean Fuels Fund to continue conducting the
Multiple Air Toxics Exposure Study (MATES-III).
|
| August 2004 |
194,742 |
|
Funds from Undesignated Fund Balance for litigation
support costs of AQMD’s enforcement case against BP West Coast Products,
et al. (“BP ARCO”).
|
| September 2004 |
22,500 |
|
Funds from other California Air Pollution Control
Districts and Air Quality Management Districts for the current upgrade of
the URBEMIS (urban emissions) model.
|
| September 2004 |
79,986 |
|
Funds from U.S. EPA Pollution Prevention Grant funds to
conduct a lubricant and rust inhibitor study.
|
| September 2004 |
350,000 |
|
Funds from the Designation for Litigation/Enforcement for
legal representation in litigation challenging the fleet rules,
architectural coatings rules, the refinery FCCU Rule 1105.1, and a CEQA
decision on a permit.
|
| October 2004 |
934,598 |
|
Funds from U.S. EPA Section 105 Grant funds for the 12th
year PAMS program ($25,960) and Section 103 Grant funds for the PM2.5
program ($591,208) and the National Air Toxics Monitoring program
($317,430).
|
| November 2004 |
$ 944,208 |
|
Funds from Undesignated Fund Balance, using a portion of
the June 2004 litigation settlement from a major refinery, to restore, and
fund for the remainder of the fiscal year, 19 critically needed positions
that were unfunded in the adopted FY 2004-05 budget.
|
| December 2004 |
130,000 |
|
Funds from Undesignated Fund Balance for legislative
representation in Sacramento, California.
|
| December 2004 |
350,000 |
|
Funds from Undesignated Fund Balance for CEQA, fleet
rules, architectural coatings rules, and refinery ESP rule litigations.
|
| December 2004 |
580,175 |
|
Funds from U.S. EPA for special particulate air
monitoring.
|
| January 2005 |
60,161 |
|
Funds from U.S. EPA Section 103 Grant funds for the Boiler
Tune-Up Outreach Program.
|
| February 2005 |
116,000 |
|
Funds from the Air Quality Investment Fund to administer
the “Mow Down Air Pollution 2005” lawn mower incentive program.
|
| February 2005 |
100,000 |
|
Funds from Undesignated Fund Balance for employee
relations litigation and negotiation services.
|
| February 2005 |
173,609 |
|
Funds from the Carl Moyer Fund to fully fund one Air
Quality Specialist position for expanded program administration and
technical evaluation of the Carl Moyer Program funding.
|
| March 2005 |
180,000 |
|
Funds from the Clean Fuels Fund to purchase six new hybrid
vehicles for AQMD’s Clean Air Choice advanced technology demonstration
program.
|
| March 2005 |
125,000 |
|
Funds from the Air Toxics “Hot Spots” Fund for continued
privatization of portions of the Annual Emissions Reporting program.
|
| April 2005 |
559,936 |
|
Funds from Undesignated Fund Balance for the final phase
of prosecution performed in AQMD’s enforcement case against BP West Coast
Products, et al. (“BP ARCO”).
|
| May 2005 |
$ 29,000 |
|
Funds from the Clean Fuels Fund to cosponsor the
conversion of a light-duty vehicle to a plug-in hybrid electric vehicle.
|
| June 2005 |
300,000 |
|
Funds from the Designation for Litigation/Enforcement for
legal representation in litigation challenging a CEQA decision on a
permit, fleet rules, architectural coatings rules, and the refinery ESP
rule.
|
| |
$ 7,247,915 |
|
Total Board-approved
FY 2004-05 Budget changes |
| |
|
|
|
| |
|
|
Sources of Funding:
$ 1,741,609 Interfund Transfers
$ 2,577,420 Grants/Contracts
$ 650,000 Budget Designations
$ 2,278,886 Undesignated Fund Balance |
| |
|
|
|
| |
$ 102,347,831 |
|
FY 2004-05 adopted Budget |
| |
|
|
|
| |
$ 109,595,746 |
|
FY 2004-05 ending Budget |
| |
|
|
|
/ / /
|