On April 4, 2008, the Board approved the release of Program Announcement 2008-08 to solicit projects at a cost not to exceed $6 million under the “Year 9” Carl Moyer Truck Fleet Modernization Program. These projects are evaluated on a first-come first-served basis and are submitted on a monthly basis to the Board for approval. This action is to execute fleet modernization contracts from the Carl Moyer Program Fund SB 1107 Account. This action is also to amend an award under the Carl Moyer Program to repower instead of purchase transit buses.

COMMITTEE:

Not Applicable

RECOMMENDED ACTIONS:

A. Authorize the Chairman to execute contracts under the Carl Moyer Fleet Modernization Program from the “Year 9” Carl Moyer Program Fund SB 1107 Account with the following entities:

  1. J.R.S. Trucking to replace one Class 8, 1977 model year diesel truck (1977 engine) with one Class 8 diesel truck (2007 engine or newer) in an amount not to exceed $73,181;
  2. GH Hauling to replace one Class 8, 1979 model year diesel truck (1979 engine) with one Class 8 diesel truck (2007 engines or newer) in an amount not to exceed $120,000;
  3. Omar & Sons Trucking Inc. to replace one Class 8, 1985 model year diesel truck (1984 engine) with one Class 8 diesel truck (2007 engines or newer) in an amount not to exceed $120,000;
  4. Hugo Salcedo to replace one Class 8, 1988 model year diesel truck (1988 engine) with one Class 8 diesel truck (2007 engine or newer) in an amount not to exceed $115,100;
  5. Classic Cartage Trucking Corp. to replace one Class 8, 1989 model year diesel truck (1988 engine) and one Class 8, 1990 model year diesel truck (1989 engine) with two Class 8 diesel trucks (2007 engine or newer) in an amount not to exceed $198,847;
  6. Silverwood Landscape Construction Corp. to replace one Class 8, 1986 model year diesel truck (1985 engine) with one Class 8 diesel truck (2007 engine or newer) in an amount not to exceed $46,791;
  7. Martin Produce Inc. to replace one Class 8, 1988 model year diesel truck (1988 engine) with one Class 8 diesel truck (2007 engines or newer) in an amount not to exceed $49,865;
  8. Brutto Trucking to replace one Class 8, 1980 model year diesel truck (1979 engine) with one Class 8 diesel truck (2007 engines or newer) in an amount not to exceed $107,452;
  9. Sunrise Trucking to replace one Class 8, 1989 model year diesel truck (1988 engine) with one Class 8 diesel truck (2007 engines or newer) in an amount not to exceed $115,118; and
  10. J E Dewitt Corp. to replace one Class 8, 1984 model year diesel truck (1989 engine), and one Class 8, 1988 model year diesel truck (1987 engine) with two Class 8 diesel trucks (2007 engine or newer) in an amount not to exceed $53,354.

B. Amend an award to the City of Culver City, originally awarded on October 3, 2008, for the purchase of 12 transit buses to an award for the repower of 12 transit buses for the unchanged amount of $360,000 from the Carl Moyer Program Fund SB1107 Account.
 

Barry R. Wallerstein, D.Env.
Executive Officer


Background

In 2005, a heavy-duty on-road fleet modernization program category was added to the Carl Moyer Program. The Fleet Modernization Program provides financial incentives to replace older high-polluting diesel trucks with newer lower emissions diesel and natural gas trucks. Having obligated all the funds under the “Year 8” Program, the Board, at its April 4, 2008 meeting, approved the issuance of the “Year 9” Fleet Modernization Program Announcement PA #2008-08 to solicit projects for up to $6 million from the Carl Moyer Program Fund SB1107 Account.
 

Proposal

This action is to execute heavy-duty truck fleet modernization contracts to replace pre-1990 trucks with model year 2007 and newer diesel trucks in an amount not to exceed $999,708 from the “Year 9” Carl Moyer Program Fund, SB 1107 Account.

Table 1, provides a detailed list of the proposed projects. These projects were chosen based on the first-come first-served criterion and the cost-effectiveness of NOx and PM reductions. GPS units will be installed on these trucks under an AQMD contract with a GPS vendor, and the cost will be reimbursed by the Carl Moyer Program.

Total NOx and PM reductions from the recommended projects are approximately 9.73 tons/year and 0.83 tons/year, respectively. All the recommended award recipients have agreed to complete the recommended projects by June 30, 2009.

This action is also to amend an award to the City of Culver City, which was originally awarded on October 3, 2008, for the purchase of 12 transit buses to instead approve an award for the repower of 12 transit buses for the unchanged amount of $360,000 from the Carl Moyer Program Fund SB1107 Account.
 

Outreach

In accordance with AQMD’s Procurement Policy and Procedure, a public notice advertising the RFP/RFQ and inviting bids was published in the Los Angeles Times, the Orange County Register, the San Bernardino Sun, and Riverside County Press Enterprise newspapers to leverage the most cost-effective method of outreach to the entire South Coast Air Basin. Also, staff has held several public workshops in the South Coast Air Basin, advertised in a trade journal, and has used consultants for outreach purposes.

Additionally, potential bidders may have been notified utilizing AQMD’s own electronic listing of certified minority vendors.  Notice of the RFP/RFQ have been mailed to the Black and Latino Legislative Caucuses and various minority chambers of commerce and business associations, the State of California Contracts Register website, and placed on the Internet at AQMD’s Web site (http://www.aqmd.gov where it can be viewed by making menu selections “Inside AQMD”/“Employment and Business Opportunities”/“Business Opportunities” or by going directly to http://www.aqmd.gov/rfp/index.html).  Information is also available on AQMD’s bidder’s 24-hour telephone message line (909) 396-2724.
 

Benefits to AQMD

The successful implementation of the proposed projects will help the AQMD significantly reduce NOx and PM10 emissions in a cost effective and expeditious manner. The vehicles funded under this program will operate many years and will provide long-term emissions reductions.
 

Resource Impacts

The total project cost of $999,708 for the proposed truck fleet modernization projects will be funded from the “Year 9” Carl Moyer Program Fund SB 1107 Account.
 

Attachment (DOC, 46k)

Table 1: Proposed Heavy-Duty Truck Fleet Modernization Projects